Regional subsidiary of Russian ore maker completes stage 1 of Skipovoy shaft overhaul
Stage 1 of Skipovoy shaft overhaul has been completed at Gorno-Shorskiy subsidiary of Evrazruda, an ore maker. According to the company’s spokesperson, both conductor threads were replaced at the beginning of March, with the total length of 96 upgraded conductors coming to over 1 kilometer. The new skips placed at the curb level were lined with armour to improve their durability and are now fit for being installed.
The old skips are to be dismantled between March 17 and April 1 and replaced with the new ones having the sliding shutter rather than the flap gate.
The final stage of the overhaul will be devoted to the replacements of more skips in the summer of 2006.
The old skips are to be dismantled between March 17 and April 1 and replaced with the new ones having the sliding shutter rather than the flap gate.
The final stage of the overhaul will be devoted to the replacements of more skips in the summer of 2006.
Код для вставки в блог | Подписаться на рассылку | Распечатать |
Другие материалы по теме:
- Gorno-Shorsky branch of Evrazruda JSC starts modernization of small skip ma ...
- Evrazruda gives overhaul to groove gigs at Kazskiy subsidiary
- Evrazruda JSC to give overhaul to mine pulling units of Kazskiy subsidiary
- Overhaul of winder completed at Kazskiy subsidiary of Evrazruda
- Evrazruda’s Abagurskiy subsidiary completes equipment overhaul