Coal Company of Chelyabinsk JSC assesses its success in six months of 2006

Throughout January to June 2006, the company has taken 1401.1 tons of clean coal. The overburden operations at Korkinksiy mine resulted in 2,261,000 cubic meters of ground, which makes up 98.5% of the planned amount.

The company’s technicians worked through 4234 meters in terms of development working.

Coal Company of Chelyabinsk JSC has shipped 1,260,600 tons of solid fuel in January to June 2006, most of which (733,600 tons) went to South Ural State District Power Plant, the spokesperson for the company’s economic department said to UrBC representative.

Другие материалы по теме: